The Construction (Design and Management) Regulations (or 'CDM Regulations') are intended to ensure that health and safety issues are properly considered during a project’s development so the risk of harm to those who have to build, use and maintain structures is reduced.
They were introduced in 1994 and came into force on 31 March 1995. They were substantially revised in 2007.
The regulations impose duties on:
- The client.
- Designers.
- The CDM co-ordinator.
- The principal contractor.
- Contractors.
- Workers.
The regulations define construction work as '...the carrying out of any building, civil engineering or engineering construction work'.
The regulations define contractors as '...any person (including a client, principal contractor or other person referred to in these Regulations) who, in the course or furtherance of a business, carries out or manages construction work'. This is as opposed to the 'principal contractor' whose role is to plan, manage and co-ordinate health and safety during construction.
The duties of contractors include:
- Ensuring the client is aware of their duties under the regulations.
- Planning, managing and monitoring their own work and that of their workers so that as far as is reasonably practicable, it is carried out without risks to health and safety.
- Ensuring that sub-contractors are informed of the minimum amount of time that will be allowed for planning and preparation (the CDM planning period).
- Providing appropriate site inductions, information and training for their workers.
- Preventing access by unauthorised persons.
- Ensuring that adequate welfare facilities are provided.
Where projects are notifiable under the regulations (projects which last more than 30 days or involve more than 500 person-days of construction work), the contractor must also:
- Ensure that a CDM co-ordinator and principal contractor have been appointed.
- Have access to the construction phase plan.
- Ensure that the Health and Safety Executive (HSE) has been notified before work starts.
- Co-operate with the principal contractor in planning and managing work.
- Provide information necessary for the health and safety file.
- Comply with site rules and the construction phase plan and take appropriate action to ensure health and safety where it is not possible to comply with the construction phase plan.
- Provide the principal contractor with details to of any sub-contractors.
- Provide information needed for the health and safety file.
- Inform the principal contractor of any changes needed to the construction phase plan.
- Inform the principal contractor of reportable incidents or accidents.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Classroom electrician courses a 'waste of money'
Say experts from the Electrical Contractors’ Association.
Wellbeing in Buildings TG 10/2025
BSRIA topic guide updates.
With brief background and WELL v2™.
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.